Improving Energy Efficient Public Schools

Call title: Improving Energy Efficient Public Schools

The modernization of the schools included thermal insulation, replacement of doors and windows, reconstruction of the heating system and installation of solar panel system. During project implementation building management system was also established, by this the current consumption of the building can be optimized and monitored. with The users and operators of the building were involved to awareness raising and capacity-building activities in order to demonstrate energy-conscious behaviors.

Thanks to the developments, the available energy saving is: 4,284.12 MWh/year and the available CO2 reduction and/or avoidance is: 892.84 t/year.

Grant decision: 2016.04.28.

Maximum grant rate: 85 %

Project Code Project Title Project Promoter Total Budget (HUF) Total Budget (EUR) Grant Amount (HUF) Grant Amount (EUR) Grant Rate
HU02-0002-A1-2013 Energetical modernization of Vak Bottyán János Primary School in Siófok Municipality of Siófok 124 493 655 HUF € 439 286 105 819 606 HUF € 373 393 85 %
HU02-0003-A1-2013 Solar era of Galamb József Agricultural Secondary School József Galamb Agricultural Secondary School 245 378 236 HUF € 865 837 208 571 501 HUF € 735 961 85 %
HU02-0004-A1-2013 Improving energy efficiency and consciousness in Ady Endre Secondary School, Debrecen Debrecen Municipality 160 008 565 HUF € 564 603 136 007 280 HUF € 479 913 85 %
HU02-0006-A1-2013 The energy efficiency renovation of Ferenc Móra Grade School Municipality of Capital City of Budapest District XIV. Zugló 297 003 251 HUF € 1 048 000 252 452 763 HUF € 890 800 85 %
HU02-0007-A1-2013 Improving energy efficiency and consciuosness in Hatvani István Elementary School, Debrecen Debrecen Municipality 161 204 182 HUF € 568 822 137 023 555 HUF € 483 499 85 %
HU02-0008-A1-2013 The energy efficiency renovation of TISZKK Secondary Technical and Vocational School of Trade, Catering and Tourism Vocational Training Centre of Tatabánya 162 509 709 HUF € 574 311 138 133 251 HUF € 487 414 84,87 %

Creation of 1,6MW Production Capacity Biogas Power Plant at Balatonszabadi

Call title: Creation of 1,6MW Production Capacity Biogas Power Plant at Balatonszabadi

Thanks to the establishment of the biogas unit, the available CO2 reduction and/or avoidance is: 10,033.03 t/year, which covers the environmental friendly, renewable energy based electric energy of ca. 2.500 households.

Grant decision: 2016.04.27.

Maximum grant rate: 49 %

Project Code Project Title Project Promoter Total Budget (HUF) Total Budget (EUR) Grant Amount (HUF) Grant Amount (EUR) Grant Rate
HU02-0007-D1-2016 Creation of 1,6MW Production Capacity Biogas Power Plant at Balatonszabadi ENERGREEN Electricity Production Producing Ltd. 1 455 409 556 HUF € 4 792 260 709 408 992 HUF € 2 335 887 48,74 %

The Biogas plant of G&A Biogas and Algal Products producing ltd

Call title: The Biogas plant of G&A  Biogas and Algal Products producing ltd

Grant decision: 2016.04.27.

Maximum grant rate: 49 %

Project Code Project Title Project Promoter Total Budget (HUF) Total Budget (EUR) Grant Amount (HUF) Grant Amount (EUR) Grant Rate
HU02-0006-D1-2016 The Biogas plant of G&A Biogas and Algal Products producing ltd G&A Biogas and Algal Products Producing Ltd. 1 284 402 764 HUF € 4 229 183 629 357 354 HUF € 2 072 299 49%